Pabna, Nov 17 (V7N) – Electricity generated by the first unit of the Rooppur Nuclear Power Plant may be connected to Bangladesh’s national grid on a trial basis within November, potentially ending the long wait for power generation from the country’s first nuclear power facility.

Several project-related sources told the media that preparations are underway to connect electricity from the plant’s first unit to the national grid this month, provided there are no technical complications or unexpected developments.

Preliminary activities for trial generation have already progressed, while coordination among various technical systems is ongoing. An initial supply target of 300 megawatts has been set, subject to approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA).

BAERA Chairman Dr Mahmudul Hasan said the exact date for starting electricity supply to the national grid could not yet be confirmed. However, efforts are underway to begin the process as soon as possible.

He said every stage of generation and supply would be closely examined after the trial connection. Although no apparent problems have been identified so far, the formal inauguration would take place only after all necessary checks were completed.

Expressing hope that Prime Minister Tarique Rahman would attend the inauguration as the chief guest, Hasan said Russian President Vladimir Putin might also join the event through a video conference.

Considering the possible participation of top leaders from both countries, relevant sources said a formal inauguration was being planned for December. However, no date has yet been finalised.

The BAERA chairman added that the inauguration schedule would also depend on when the prime minister would be available to attend the event. For this reason, it was not yet possible to announce a specific date.

He said electricity supply from the first unit would initially begin at around 300 megawatts before being increased gradually. Reaching full production capacity and supplying that amount of electricity to the national grid could take another five to six months.

Accordingly, the first unit is expected to reach its full generation capacity sometime between April and June next year.

According to project-related sources, the first unit could generate approximately 30 to 35 per cent of its full electrical output once the reactor reaches 40 per cent of its thermal capacity. Based on this calculation, the initial plan is to supply around 300 megawatts to the national grid.

However, connecting the plant to the grid will not immediately mean the start of regular electricity supply.

Following the trial connection, generation and supply operations will be monitored closely for several days to identify any technical faults or operational problems. If the results are satisfactory, the plant will seek the necessary approval from BAERA before formally inaugurating electricity supply.

The Rooppur Nuclear Power Plant is being constructed in Ishwardi upazila of Pabna with Russian nuclear technology, financing and technical assistance. The project is being implemented by Atomstroyexport, the engineering division of Russia’s state-owned nuclear corporation Rosatom.

The plant has two units, each with a generation capacity of 1,200 megawatts. Once both units become fully operational, they are expected to contribute a combined 2,400 megawatts of electricity to Bangladesh’s national grid.

END/MSR/SMA/